Heister Remodel Preliminary Design 5
Heister Kitchen Review
Heister Master Bath Review
RFI’s (information needed)*******************
OB – truss detail – completed
OB – check on engineering for depressed shower – to be determined
Engineer – structural options for creating the opening between kitchen and living room
Scope of Work
Kitchen
– Remove existing and Remodel
– Install new Sliding door and Window
– Enlarge opening between kitchen and living room
– Enlarge opening between living room and hall
Master Bathroom
– Remove Existing & Remodel
– Install “no curb” shower if possible using existing drain
Master Bedroom – Install new window
Guest Bathroom Remodel – new tile
Create new TV area above fireplace and re do fireplace
Entire House
Replace flooring throughout house – “light maple wide plank look” vinyl flooring
Replace 5 interior doors with single panel door – m. bath with white glass panel
Re-pipe all plumbing lines
Install new recessed lighting throughout house – 4″ LEDs
Install new roof – remove old pool heating
Fixtures and Appliances ***********************************************
Kitchen
New Fridge 36 x 24 counter depth – are you purchasing new fridge- YES
Ex range 30 x24
Range Hood What model ? Inset in wood
Microwave 24 “ wide What model ?
Dishwasher – Model
Back splash
Sink
Faucet
Soap dispener
Filtered water faucet
Disposal with air switch
Countertop material?
2 Pendant lights over island
“Owner” Bath
Sink
Sink faucet
Shower faucet
Shower drain for curbless
Shower Tile
Floor tile
Hand bars ?
Towel bars, toilet etc.
Niche
Electric mirror
Counter
Cabinets – light wood
Guest Bath
Sink
Sink faucet
Shower
Shower faucet
Tile
Counter
Cabinets – light wood
Approximate Timeline
The following is an estimated schedule months:
Construction Documents
Drafting week 0 – 6 Commenced 4.26.24
Online conference #1 –COMPLETE 5.13.24
Planning Department Submission approx. week 3 – 5 – COMPLETE 5.10.24
Energy Engineering week 6 – 8 – In process
Engineering week 6 – 14 – In Que
Plan Review and Submission to City
Building Department Submission week 15 – 20
Corrections from Building Department week 20 – 30
Online conference #2 if necessary
Resubmittal
Permit