Approximate Timeline
Approximate Timeline **********************
The following is an estimated schedule 5 months:
Drafting weeks 0 – 6 Feb 22
Online conference #1
Planning Department Submission week 4 – 6 – Approved Mar 13
Submitted Feb 29
Energy Engineering week 6 – 8 – In Process
Engineering week 6 – 14 – – In Process
Plan Review and Submission to City
Building Department Submission week 15 – 20
Online conference #2 if necessary
Corrections from Building Department week 20 – 30
Resubmittal
Permit
Specifications – RFI’s –
Specifications – RFI’s – *************************************************************
Flooring in room
Flooring stairs – suggestion painted plywood with bullnose
Stairway railing – standard
Stairway guardrail or pony wall above –
Lighting – suggestion recessed LED 4”
Cabinetry / Finish Carpentry
Storage
Ceiling ?
Casing and Baseboard – suggest flat 6” base 4” casing
Exposed beams – there will be a structural beam in the center
We could add decorative beams for visual