Addition – La Luna Ojai

Approximate Timeline

Approximate Timeline **********************
The following is an estimated schedule 5 months:

Drafting weeks 0 – 6 Feb 22
Online conference #1

Planning Department Submission week 4 – 6Approved Mar 13
Submitted Feb 29

Energy Engineering week 6 – 8In Process

Engineering week 6 – 14 – – In Process

Plan Review and Submission to City

Building Department Submission week 15 – 20
Online conference #2 if necessary

Corrections from Building Department week 20 – 30
Resubmittal

Permit

Specifications – RFI’s –

Specifications – RFI’s – *************************************************************
Flooring in room
Flooring stairs – suggestion painted plywood with bullnose
Stairway railing – standard
Stairway guardrail or pony wall above –

Lighting – suggestion recessed LED 4”

Cabinetry / Finish Carpentry
Storage
Ceiling ?
Casing and Baseboard – suggest flat 6” base 4” casing
Exposed beams – there will be a structural beam in the center
We could add decorative beams for visual