Remodel Ojai – Cook – House

222 Avenida de la Vereda – Ojai

Garage

6.23.18

Ojai Remodel garage

Ojai Remodel garage

Ojai Remodel garage

Ojai Remodel garage

Proposed Floor Plan

4.16.18

 

Master Bath

Kitchen

 

 

 

Proposed Floor Plan

4.14.18

Master Bath

  • Shower, toilet on East wall
  • Trough sink, storage cabinet
  • Do you want a shampoo niche ?
  • Bench ?

Bath West Elevation

  • storage cabinet – open section?  Counter ? or all closed?
  • Only about 12″ deep with this wall config
  • might be good to push the bath wall further into the closet

Bath East Elevation

Kitchen

  • May have put the open shelves on wrong side ?
  • Farm sink
  • Grayish cabinets, white tops
  • Wolf Range 48″

 

 

Existing house

Existing plan

4.13.2018 site meeting with Lester and Katie

4.12.2018 notes from Lester

Plan of attack
Priorities

  • make house safe
  • new roof/gutters
  • hvac
  • septc
  • plumbing
  • electrical updates

1st priority – Garage conversion

  • add washer/dryer and
  • finish interior with drywall/insulation
  • plus exterior carport
  • master bedroom/bathroom re-configuration taking potential
    real estate from kitchen and hall closet
  • hardwood floors throughout
  •  Kitchen remodel

Phase 2?

  • Kids bathroom update
  • We want to try to tackle fencing, painting exterior and
    interior of house ourselves??